How does this schedule turn delay into exposure?
Find the milestone that starts the clock. Write the rate as dollars per named period, and whether the period is a calendar day, a business day or a week. Write what stops the clock: an extension of time actually granted, a relief event, or nothing. Write when accrual ends: commencement, practical completion, termination, or a stated number of days. Then write what else still sits outside that clause: indemnities, abatement, general damages, or a call on performance security.
If the pack uses a weekly rate, record the rounding rule for a part-week before you model. If the pack is silent, the model is unfinished. GST treatment belongs on the same note as the rate. This page models GST exclusive.
This is a bid/no-bid filter, not legal advice. Send counsel the clause, the rate, and the question of whether the figure is open to challenge. Do not bring a penalty-versus-genuine-pre-estimate conclusion back from the bid room.